Windows and sliding doors
Typically 10 to 14 weeksSized from the permit set, in frames made for salt air.
Clock two: the container
Counted from the day we place the order to the day it reaches your lot. These are samples, and your written quote lists each one for your plan.
These can't be ordered until the plans are final, and many can't be changed once they are.
Sized from the permit set, in frames made for salt air.
Standard sizes are quicker than custom.
Built after the layout is signed.
Engineered to your plan and your wind rating.
Usually on a shelf. Not always.
Treated for termites where the plans call for it.
Common profiles on hand, special colors by order.
Common styles on hand, specials by order.
Basics on hand. A particular finish may come by sea.
Check the model before the plans are final: sizes differ.
Chosen from what's available when you decide.
No container to wait for.
Scheduled around the pour and the inspector.
Sample lead times. Mills, sailing schedules and demand change them, so we confirm each on your written quote.
Why it runs long
A window for a house on Oahu starts as an order on the mainland. It waits for a production slot, is built, is crated, waits for a booking on a ship, sails, clears the harbor and is trucked to your lot. The sailing is the shortest step in that list.
That's why we don't tell you a build date until we have your lead times in writing. The build can't start on the unit's frame until the trusses are on site, and the shell can't be weather-tight until the windows are.
We would rather give you a long, honest range than a short one we'd have to take back.
What we do about the wait
Windows, cabinets and trusses go first. At your risk, they can go before approval. We say which ones are worth it.
Materials arrive when the crew can use them, so nothing sits in the rain.
Lumber and cabinets are kept dry and off the ground, away from termites.
We put two weeks between a delivery and the job that needs it.
If an item is late, we offer alternatives with their lead times and their price. Nothing changes without your signature.
You hear from us the day we hear from the supplier.
Trusses and beams
Trusses are engineered to your roof, your wind rating and the loads on them. That makes them the first item on the list and the hardest to change.
If the city asks for a change to the roof in review, a truss order already placed has to be remade. That's why we hold trusses for approval unless you tell us to order at risk.

Questions
Your estimate says how long its numbers hold. After that date, items ordered later are priced on the day of the order, and we tell you before we place it.
We tell you the day we hear. If the late item holds up other work, we show you the options, and the cost of each, in writing.
Yes, in many cases. You take on the lead time and the sizes. We need them in hand, or at least confirmed, before we frame the openings.
Because plans change in review. An item made to the old plan is yours to pay for. We order what's safe early and hold the rest.
After a lot visit you get a sheet like this one, written for your unit.